Contract Bid Abstract
CP 792 - Rapidan Dam West Wall Repairs | PCiRoads, LLC | Engineering & Construction Innovations, Inc | Kraemer North America, LLC | MEYER CONTRACTING INC. | |||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Unit Price | Total Price | Unit Price | Total Price | Unit Price | Total Price | ||||||
2105.601 | EXCAVATION | LS | 1 | $16,000.00 | $16,000.00 | $10,000.00 | $10,000.00 | $2,850.00 | $2,850.00 | $12,500.00 | $12,500.00 |
2105.601 | REMOVAL | LS | 1 | $130,000.00 | $130,000.00 | $189,000.00 | $189,000.00 | $6,000.00 | $6,000.00 | $22,340.00 | $22,340.00 |
2105.601 | REMOVAL AND REINSTALL | LS | 1 | $45,000.00 | $45,000.00 | $1,000.00 | $1,000.00 | $15,000.00 | $15,000.00 | $9,100.00 | $9,100.00 |
2105.601 | INCIDENTALS | LS | 1 | $40,000.00 | $40,000.00 | $45,000.00 | $45,000.00 | $64,000.00 | $64,000.00 | $269,800.00 | $269,800.00 |
2301.507 | CONCRETE | C Y | 250 | $650.00 | $162,500.00 | $445.00 | $111,250.00 | $1,116.00 | $279,000.00 | $755.00 | $188,750.00 |
2302.602 | DOWELS | EACH | 1,600 | $15.00 | $24,000.00 | $17.00 | $27,200.00 | $75.40 | $120,640.00 | $36.00 | $57,600.00 |
2401.508 | REINFORCING | LB | 11,000 | $1.00 | $11,000.00 | $2.95 | $32,450.00 | $1.93 | $21,230.00 | $2.30 | $25,300.00 |
2401.603 | WATERSTOP | L F | 800 | $3.00 | $2,400.00 | $3.00 | $2,400.00 | $38.00 | $30,400.00 | $9.10 | $7,280.00 |
2401.618 | VERTICAL FORMS | S F | 2,800 | $6.00 | $16,800.00 | $25.00 | $70,000.00 | $82.00 | $229,600.00 | $61.00 | $170,800.00 |
2411.602 | ROCK ANCHORS | EACH | 30 | $1,200.00 | $36,000.00 | $200.00 | $6,000.00 | $800.00 | $24,000.00 | $4,000.00 | $120,000.00 |
2433.602 | WEEP HOLE DRAIN | EACH | 21 | $125.00 | $2,625.00 | $60.00 | $1,260.00 | $785.00 | $16,485.00 | $330.00 | $6,930.00 |
2433.602 | 20' HORIZONTAL DRAIN | EACH | 1 | $6,100.00 | $6,100.00 | $7,325.00 | $7,325.00 | $15,000.00 | $15,000.00 | $11,300.00 | $11,300.00 |
2503.617 | GROUT | C F | 1,650 | $21.28 | $35,112.00 | $28.00 | $46,200.00 | $72.00 | $118,800.00 | $46.00 | $75,900.00 |
2545.501 | ELECTRICAL SYSTEM CONDUIT | LS | 1 | $16,000.00 | $16,000.00 | $16,000.00 | $16,000.00 | $4,500.00 | $4,500.00 | $7,980.00 | $7,980.00 |
Totals for project CP 792 | $543,537.00 | $565,085.00 | $947,505.00 | $985,580.00 | |||||||
Contract Total: | $543,537.00 | $565,085.00 | $947,505.00 | $985,580.00 |