SAP 07-632-13 - CSAH 32 OVERLAY | Central Specialties, Inc. | OMG Midwest Inc. dba Minnesota Paving & Materials | KNIFE RIVER | DUININCK BROTHERS INC |
Item No. | Item | Units | Quantity | Unit Price | Total Price | Unit Price | Total Price | Unit Price | Total Price | Unit Price | Total Price |
2118.501 | AGGREGATE SURFACING CLASS 2 MOD | TON | 294 | $30.00 | $8,820.00 | $32.00 | $9,408.00 | $32.00 | $9,408.00 | $56.00 | $16,464.00 |
2221.501 | AGGREGATE SHOULDERING CLASS 1 MOD | TON | 5,653 | $19.00 | $107,407.00 | $20.20 | $114,190.60 | $20.00 | $113,060.00 | $20.35 | $115,038.55 |
2232.501 | MILL BITUMINOUS SURFACE | S Y | 1,939 | $5.00 | $9,695.00 | $3.50 | $6,786.50 | $5.00 | $9,695.00 | $3.00 | $5,817.00 |
2357.502 | BITUMINOUS MATERIAL FOR TACK COAT | GAL | 9,632 | $0.01 | $96.32 | $2.00 | $19,264.00 | $0.01 | $96.32 | $0.01 | $96.32 |
2360.501 | TYPE SP 19.0 WEARING COURSE MIX (2,B) | TON | 16,718 | $56.89 | $951,087.02 | $58.00 | $969,644.00 | $62.00 | $1,036,516.00 | $71.88 | $1,201,689.84 |
2580.501 | TEMPORARY LANE MARKING | LIN FT | 5,960 | $0.75 | $4,470.00 | $1.50 | $8,940.00 | $0.40 | $2,384.00 | $1.51 | $8,999.60 |
| Totals for project SAP 07-632-13 | | $1,081,575.34 | | $1,128,233.10 | | $1,171,159.32 | | $1,348,105.31 |
|
Contract Total: | $1,081,575.34 | $1,128,233.10 | $1,171,159.32 | $1,348,105.31 |