Bid Abstract

SP 07-612-10 - CSAH 12 BRIDGE NO. 07589 & GRADINGLUNDA CONSTRUCTION CO. AMES CONSTRUCTION, INC. MINNOWA CONSTRUCTION CO. ROBERT SCHROEDER CONSTRUCTION INC. KRAEMER NORTH AMERICA C.S. McCROSSAN CONSTRUCTION, INC. PARK CONSTRUCTION CO. S.M. HENTGES & SONS INC. 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLUMP SUM1$207,400.00$207,400.00$159,000.00$159,000.00$70,000.00$70,000.00$246,175.00$246,175.00$155,000.00$155,000.00$185,000.00$185,000.00$191,185.00$191,185.00$152,407.30$152,407.30
2041.610TRAINEESHOUR900$1.00$900.00$1.00$900.00$1.00$900.00$0.50$450.00$1.00$900.00$1.00$900.00$1.25$1,125.00$1.06$954.00
2101.511CLEARING AND GRUBBINGLUMP SUM1$982.45$982.45$5,000.00$5,000.00$500.00$500.00$2,500.00$2,500.00$1,000.00$1,000.00$5,000.00$5,000.00$4,715.00$4,715.00$61,881.40$61,881.40
2104.501REMOVE PIPE DRAINLIN FT1,511$4.33$6,542.63$7.00$10,577.00$5.00$7,555.00$1.00$1,511.00$4.50$6,799.50$5.40$8,159.40$2.10$3,173.10$8.41$12,707.51
2104.503REMOVE BITUMINOUS WALKSQ FT21,380$0.27$5,772.60$0.40$8,552.00$0.15$3,207.00$0.27$5,772.60$0.30$6,414.00$0.35$7,483.00$0.29$6,200.20$0.25$5,345.00
2104.513SAWING BITUMINOUS PAVEMENT (FULL DEPTH)LIN FT110$4.99$548.90$4.00$440.00$4.00$440.00$5.00$550.00$5.00$550.00$3.50$385.00$5.05$555.50$1.57$172.70
2105.501COMMON EXCAVATION (P)CU YD179,230$1.32$236,583.60$2.70$483,921.00$1.85$331,575.50$1.32$236,583.60$1.35$241,960.50$2.35$421,190.50$3.30$591,459.00$6.84$1,225,933.20
2106.607SELECT GRANULAR EMBANKMENT MODIFIED 10% (CV) (P)CU YD5,698$14.25$81,196.50$14.00$79,772.00$14.00$79,772.00$14.25$81,196.50$14.50$82,621.00$14.50$82,621.00$22.10$125,925.80$18.99$108,205.02
2123.610TRACTOR MOUNTED BACKHOEHOUR20$98.92$1,978.40$92.00$1,840.00$110.00$2,200.00$100.00$2,000.00$100.00$2,000.00$120.00$2,400.00$172.00$3,440.00$39.39$787.80
2123.610CRAWLER MOUNTED BACKHOEHOUR10$139.02$1,390.20$132.00$1,320.00$200.00$2,000.00$120.00$1,200.00$150.00$1,500.00$135.00$1,350.00$172.00$1,720.00$87.72$877.20
2211.501AGGREGATE BASE CLASS 2TON1,480$14.73$21,800.40$15.00$22,200.00$18.00$26,640.00$18.00$26,640.00$18.45$27,306.00$19.50$28,860.00$20.80$30,784.00$19.51$28,874.80
2211.501AGGREGATE BASE CLASS 2 MODIFIEDTON950$16.12$15,314.00$15.00$14,250.00$19.00$18,050.00$18.00$17,100.00$21.25$20,187.50$20.50$19,475.00$21.90$20,805.00$20.60$19,570.00
2360.501TYPE SP 19.0 WEARING COURSE MIXTURE (2,B)TON550$71.75$39,462.50$71.75$39,462.50$75.00$41,250.00$72.00$39,600.00$71.75$39,462.50$81.50$44,825.00$73.80$40,590.00$81.30$44,715.00
2401.501STRUCTURAL CONCRETE (3Y43) (P)CU YD1,239$450.00$557,550.00$363.00$449,757.00$450.00$557,550.00$400.00$495,600.00$500.00$619,500.00$450.00$557,550.00$348.00$431,172.00$449.14$556,484.46
2401.501STRUCTURAL CONCRETE (1A43) (P)CU YD659$425.00$280,075.00$250.00$164,750.00$300.00$197,700.00$260.00$171,340.00$250.00$164,750.00$395.00$260,305.00$222.00$146,298.00$336.67$221,865.53
2401.512BRIDGE SLAB CONCRETE (3Y36A) (P)SQ FT17,290$12.00$207,480.00$10.00$172,900.00$10.00$172,900.00$12.00$207,480.00$9.60$165,984.00$15.00$259,350.00$24.00$414,960.00$17.29$298,944.10
2401.513TYPE P-2 (TL-4) RAILING CONCRETE (3Y46A) (P)LIN FT524$44.00$23,056.00$46.00$24,104.00$55.00$28,820.00$60.00$31,440.00$45.35$23,763.40$85.00$44,540.00$44.60$23,370.40$56.58$29,647.92
2401.541REINFORCEMENT BARS (P)POUND51,770$0.80$41,416.00$0.75$38,827.50$0.90$46,593.00$1.00$51,770.00$0.75$38,827.50$0.85$44,004.50$0.72$37,274.40$0.87$45,039.90
2401.541REINFORCEMENT BARS (EPOXY COATED) (P)POUND255,940$0.90$230,346.00$0.80$204,752.00$1.00$255,940.00$1.05$268,737.00$0.90$230,346.00$0.95$243,143.00$0.72$184,276.80$0.92$235,464.80
2401.601STRUCTURE EXCAVATION (P)LUMP SUM1$7,500.00$7,500.00$38,000.00$38,000.00$25,000.00$25,000.00$65,000.00$65,000.00$25,000.00$25,000.00$30,000.00$30,000.00$59,800.00$59,800.00$23,548.78$23,548.78
2402.583ORNAMENTAL METAL RAILING TYPE SPECIAL 2 (P)LIN FT95$135.00$12,825.00$155.00$14,725.00$160.00$15,200.00$150.00$14,250.00$155.00$14,725.00$175.00$16,625.00$167.00$15,865.00$154.93$14,718.35
2402.583ORNAMENTAL METAL RAILING TYPE SPECIAL 1 (P)LIN FT200$100.00$20,000.00$115.00$23,000.00$120.00$24,000.00$140.00$28,000.00$115.00$23,000.00$135.00$27,000.00$122.00$24,400.00$107.62$21,524.00
2402.584STRUCTURAL TUBE RAILING DESIGN T-1 (P)LIN FT512$70.00$35,840.00$76.00$38,912.00$90.00$46,080.00$100.00$51,200.00$80.00$40,960.00$85.00$43,520.00$91.40$46,796.80$81.39$41,671.68
2402.591EXPANSION JOINT DEVICES TYPE 5 (P)LIN FT224$100.00$22,400.00$155.00$34,720.00$150.00$33,600.00$150.00$33,600.00$150.00$33,600.00$220.00$49,280.00$149.00$33,376.00$91.97$20,601.28
2402.595BEARING ASSEMBLY (P)EACH40$650.00$26,000.00$520.00$20,800.00$650.00$26,000.00$850.00$34,000.00$650.00$26,000.00$625.00$25,000.00$451.00$18,040.00$654.37$26,174.80
2404.501CONCRETE WEARING COURSE (3U17A) (P)SQ FT13,795$4.00$55,180.00$4.28$59,042.60$4.28$59,042.60$4.00$55,180.00$4.28$59,042.60$4.50$62,077.50$4.10$56,559.50$4.66$64,284.70
2405.502PRESTRESSED CONCRETE BEAMS MN54 (P)LIN FT2,184$145.00$316,680.00$150.00$327,600.00$170.00$371,280.00$220.00$480,480.00$160.00$349,440.00$155.00$338,520.00$166.00$362,544.00$142.62$311,482.08
2405.511DIAPHRAGMS FOR TYPE MN54 PREST BEAMSLIN FT366$70.00$25,620.00$50.00$18,300.00$70.00$25,620.00$65.00$23,790.00$60.00$21,960.00$55.00$20,130.00$130.00$47,580.00$80.50$29,463.00
2452.507C-I-P CONCRETE PILING DELIVERED 12"LIN FT16,165$23.00$371,795.00$32.00$517,280.00$26.00$420,290.00$20.00$323,300.00$38.00$614,270.00$36.50$590,022.50$33.10$535,061.50$14.05$227,118.25
2452.508C-I-P CONCRETE PILING DRIVEN 12"LIN FT16,165$1.00$16,165.00$1.00$16,165.00$1.00$16,165.00$4.00$64,660.00$1.00$16,165.00$1.00$16,165.00$1.25$20,206.25$6.36$102,809.40
2452.519C-I-P CONCRETE TEST PILE 95 FT LONG 12"EACH2$4,500.00$9,000.00$3,300.00$6,600.00$8,000.00$16,000.00$3,000.00$6,000.00$4,500.00$9,000.00$4,500.00$9,000.00$3,630.00$7,260.00$2,154.01$4,308.02
2452.519C-I-P CONCRETE TEST PILE 105 FT LONG 12"EACH4$4,700.00$18,800.00$3,500.00$14,000.00$10,000.00$40,000.00$4,000.00$16,000.00$5,500.00$22,000.00$5,000.00$20,000.00$4,460.00$17,840.00$2,720.84$10,883.36
2452.519C-I-P CONCRETE TEST PILE 110 FT LONG 12"EACH4$4,800.00$19,200.00$3,700.00$14,800.00$11,000.00$44,000.00$4,500.00$18,000.00$6,000.00$24,000.00$4,750.00$19,000.00$4,900.00$19,600.00$2,947.58$11,790.32
2452.602PILE ANALYSISEACH10$1,350.00$13,500.00$1,500.00$15,000.00$2,500.00$25,000.00$1,200.00$12,000.00$2,100.00$21,000.00$2,500.00$25,000.00$3,540.00$35,400.00$2,691.80$26,918.00
2452.603BITUMEN PILE COATINGLIN FT7,068$4.00$28,272.00$6.35$44,881.80$10.00$70,680.00$3.50$24,738.00$8.25$58,311.00$11.50$81,282.00$11.90$84,109.20$1.62$11,450.16
2501.51112" RC PIPE CULVERT CLASS VLIN FT64$20.19$1,292.16$30.00$1,920.00$24.00$1,536.00$26.00$1,664.00$20.60$1,318.40$21.50$1,376.00$28.70$1,836.80$26.60$1,702.40
2501.51512" RC PIPE APRONEACH3$376.66$1,129.98$430.00$1,290.00$300.00$900.00$150.00$450.00$385.50$1,156.50$345.00$1,035.00$553.00$1,659.00$319.51$958.53
2502.502DRAINAGE SYSTEM TYPE (B910)LUMP SUM1$2,000.00$2,000.00$3,000.00$3,000.00$5,000.00$5,000.00$2,500.00$2,500.00$3,000.00$3,000.00$3,500.00$3,500.00$4,090.00$4,090.00$3,722.22$3,722.22
2502.52112" RC PIPE DRAINLIN FT1,100$17.62$19,382.00$25.00$27,500.00$24.00$26,400.00$17.62$19,382.00$18.00$19,800.00$21.50$23,650.00$20.00$22,000.00$24.98$27,478.00
2503.54112" RC PIPE SEWER DESIGN 3006 CLASS VLIN FT44$21.51$946.44$30.00$1,320.00$25.65$1,128.60$26.00$1,144.00$22.00$968.00$25.00$1,100.00$28.80$1,267.20$26.61$1,170.84
2506.501CONSTRUCT DRAINAGE STRUCTURE DESIGN A OR FLIN FT9.5$168.20$1,597.90$230.00$2,185.00$158.00$1,501.00$240.00$2,280.00$172.00$1,634.00$170.00$1,615.00$215.00$2,042.50$180.01$1,710.10
2506.516CASTING ASSEMBLYEACH1$404.66$404.66$440.00$440.00$350.00$350.00$450.00$450.00$415.00$415.00$380.00$380.00$483.00$483.00$538.22$538.22
2511.501RANDOM RIPRAP CLASS IIICU YD26.2$50.33$1,318.65$75.00$1,965.00$30.00$786.00$58.00$1,519.60$51.50$1,349.30$54.00$1,414.80$96.30$2,523.06$55.09$1,443.36
2514.501CONCRETE SLOPE PAVINGSQ YD500$55.00$27,500.00$65.00$32,500.00$75.00$37,500.00$90.00$45,000.00$110.00$55,000.00$105.00$52,500.00$72.80$36,400.00$85.97$42,985.00
2557.501WIRE FENCE DESIGN SPECIAL VINYL COATEDLIN FT510$22.85$11,653.50$24.50$12,495.00$22.85$11,653.50$24.50$12,495.00$22.85$11,653.50$26.50$13,515.00$23.10$11,781.00$26.56$13,545.60
2557.523METAL BRACE ASSEMBLY(CHAIN LINK FENCE)EACH4$286.00$1,144.00$225.00$900.00$286.00$1,144.00$200.00$800.00$286.00$1,144.00$245.00$980.00$289.00$1,156.00$216.80$867.20
2557.527ELECTRICAL GROUNDEACH3$112.00$336.00$85.00$255.00$112.00$336.00$70.00$210.00$112.00$336.00$92.00$276.00$113.00$339.00$75.88$227.64
2563.601TRAFFIC CONTROLLUMP SUM1$3,400.00$3,400.00$3,400.00$3,400.00$4,000.00$4,000.00$6,000.00$6,000.00$3,400.00$3,400.00$4,330.00$4,330.00$3,440.00$3,440.00$3,685.54$3,685.54
2573.502SILT FENCE, TYPE HEAVY DUTYLIN FT300$1.65$495.00$2.00$600.00$1.65$495.00$2.00$600.00$1.65$495.00$2.10$630.00$1.65$495.00$2.71$813.00
2573.502SILT FENCE, TYPE MACHINE SLICEDLIN FT9,380$1.51$14,163.80$1.50$14,070.00$1.51$14,163.80$1.60$15,008.00$1.51$14,163.80$1.80$16,884.00$1.55$14,539.00$1.30$12,194.00
2573.512TEMPORARY DITCH CHECK TYPE 2LIN FT100$2.38$238.00$3.00$300.00$2.38$238.00$2.50$250.00$2.38$238.00$2.70$270.00$2.40$240.00$3.25$325.00
2573.530STORM DRAIN INLET PROTECTIONEACH1$399.10$399.10$355.00$355.00$150.00$150.00$150.00$150.00$425.00$425.00$81.50$81.50$147.00$147.00$406.49$406.49
2573.550EROSION CONTROL SUPERVISORLUMP SUM1$7,918.45$7,918.45$5,000.00$5,000.00$2,000.00$2,000.00$1,000.00$1,000.00$10,000.00$10,000.00$1,630.00$1,630.00$2,530.00$2,530.00$9,023.69$9,023.69
2573.602CULVERT PROTECTIONEACH4$148.62$594.48$390.00$1,560.00$75.00$300.00$100.00$400.00$150.00$600.00$81.50$326.00$203.00$812.00$162.60$650.40
2573.602TEMPORARY ROCK CONSTRUCTION ENTRANCEEACH2$474.88$949.76$800.00$1,600.00$750.00$1,500.00$500.00$1,000.00$500.00$1,000.00$380.00$760.00$865.00$1,730.00$650.39$1,300.78
2575.501SEEDINGACRE13.1$60.00$786.00$55.00$720.50$60.00$786.00$100.00$1,310.00$60.00$786.00$110.00$1,441.00$60.70$795.17$498.63$6,532.05
2575.502SEED MIXTURE 310POUND150$14.06$2,109.00$13.00$1,950.00$14.06$2,109.00$13.38$2,007.00$14.06$2,109.00$14.50$2,175.00$14.20$2,130.00$13.01$1,951.50
2575.502SEED MIXTURE 250POUND350$1.77$619.50$1.75$612.50$1.77$619.50$1.80$630.00$1.77$619.50$1.90$665.00$1.80$630.00$2.44$854.00
2575.502SEED MIXTURE 150POUND180$1.78$320.40$1.75$315.00$1.78$320.40$1.74$313.20$1.78$320.40$1.90$342.00$1.80$324.00$2.17$390.60
2575.502SEED MIXTURE 340POUND160$4.60$736.00$4.00$640.00$4.60$736.00$3.03$484.80$4.60$736.00$3.30$528.00$4.65$744.00$4.61$737.60
2575.505SODDING TYPE EROSIONSQ YD1,380$2.25$3,105.00$2.00$2,760.00$2.25$3,105.00$3.00$4,140.00$2.25$3,105.00$3.20$4,416.00$2.30$3,174.00$4.88$6,734.40
2575.511MULCH MATERIAL TYPE 3TON7.3$110.00$803.00$115.00$839.50$110.00$803.00$120.00$876.00$110.00$803.00$130.00$949.00$111.00$810.30$260.16$1,899.17
2575.511MULCH MATERIAL TYPE 1TON18.5$90.00$1,665.00$85.00$1,572.50$90.00$1,665.00$120.00$2,220.00$90.00$1,665.00$130.00$2,405.00$91.10$1,685.35$260.16$4,812.96
2575.519DISK ANCHORINGACRE12.5$44.00$550.00$40.00$500.00$44.00$550.00$75.00$937.50$44.00$550.00$81.50$1,018.75$44.50$556.25$271.00$3,387.50
2575.523EROSION CONTROL BLANKETS CATEGORY 4SQ YD4,910$1.07$5,253.70$1.10$5,401.00$1.07$5,253.70$1.15$5,646.50$1.07$5,253.70$1.30$6,383.00$1.10$5,401.00$0.65$3,191.50
2575.532FERTILIZER TYPE 3POUND2,710$0.32$867.20$0.50$1,355.00$0.32$867.20$0.40$1,084.00$0.32$867.20$0.45$1,219.50$0.32$867.20$1.19$3,224.90
2575.532FERTILIZER TYPE 4POUND730$0.28$204.40$0.30$219.00$0.28$204.40$0.40$292.00$0.28$204.40$0.45$328.50$0.28$204.40$1.19$868.70
2575.560HYDRAULIC SOIL STABILIZER TYPE 5POUND460$1.25$575.00$2.00$920.00$1.25$575.00$2.00$920.00$1.25$575.00$2.10$966.00$1.25$575.00$4.34$1,996.40
 Totals for project SP 07-612-10 $3,073,030.26 $3,216,611.40 $3,230,226.20 $3,271,007.30 $3,333,036.20 $3,738,253.45 $3,770,874.68 $4,159,953.11
 
Contract Total:$3,073,030.26$3,216,611.40$3,230,226.20$3,271,007.30$3,333,036.20$3,738,253.45$3,770,874.68$4,159,953.11