SP 07-599-51 - RAPIDAN TWP. 96 BRIDGE NO. 07591 AND APPROACH GRADINGM-K BRIDGE CONSTRUCTION INC. DUININCK BROTHERS INC LUNDA CONSTRUCTION CO. STRUCTURAL SPECIALTIES INC. MINNOWA CONSTRUCTION CO. 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLUMP SUM0.91$44,862.02$40,824.44$55,235.00$50,263.85$33,000.00$30,030.00$60,000.00$54,600.00$50,000.00$45,500.00
2021.501MOBILIZATIONLUMP SUM0.09$44,862.02$4,037.58$55,235.00$4,971.15$33,000.00$2,970.00$117,600.00$10,584.00$50,000.00$4,500.00
2101.511CLEARING AND GRUBBINGLUMP SUM1$1,500.00$1,500.00$2,500.00$2,500.00$2,500.00$2,500.00$2,500.00$2,500.00$2,500.00$2,500.00
2105.501COMMON EXCAVATION (P)CU YD346$5.00$1,730.00$3.00$1,038.00$5.00$1,730.00$5.00$1,730.00$5.00$1,730.00
2105.523COMMON BORROW (LV)CU YD2,583$6.25$16,143.75$0.01$25.83$6.25$16,143.75$6.25$16,143.75$6.25$16,143.75
2118.607AGGREGATE SURFACING (CV) CLASS 1CU YD163$24.00$3,912.00$23.20$3,781.60$24.00$3,912.00$24.00$3,912.00$24.00$3,912.00
2401.501STRUCTURAL CONCRETE (3Y43) (P)CU YD70$650.00$45,500.00$575.00$40,250.00$1,200.00$84,000.00$591.04$41,372.80$600.00$42,000.00
2401.512BRIDGE SLAB CONCRETE (3Y33A) (P)SQ FT4,225$20.00$84,500.00$34.00$143,650.00$23.55$99,498.75$32.26$136,298.50$43.00$181,675.00
2401.541REINFORCEMENT BARS (EPOXY COATED) (P)POUND66,450$1.00$66,450.00$1.00$66,450.00$1.00$66,450.00$1.01$67,114.50$1.00$66,450.00
2401.601STRUCTURE EXCAVATIONLUMP SUM1$12,000.00$12,000.00$8,000.00$8,000.00$6,700.00$6,700.00$24,242.24$24,242.24$15,000.00$15,000.00
2401.601SLOPE PREPARATIONLUMP SUM1$5,000.00$5,000.00$8,000.00$8,000.00$3,000.00$3,000.00$17,042.56$17,042.56$4,000.00$4,000.00
2402.521STRUCTURAL STEEL (3306) (P)POUND470$3.00$1,410.00$2.00$940.00$7.50$3,525.00$2.52$1,184.40$4.00$1,880.00
2402.584STRUCTURAL TUBE RAILING DESIGN SPECIAL (P)LIN FT284$175.00$49,700.00$165.00$46,860.00$160.00$45,440.00$172.42$48,967.28$200.00$56,800.00
2442.501REMOVE EXISTING BRIDGELUMP SUM1$24,000.00$24,000.00$28,000.00$28,000.00$65,000.00$65,000.00$11,777.92$11,777.92$40,000.00$40,000.00
2452.510STEEL H-PILING DRIVEN 10"LIN FT390$1.00$390.00$1.00$390.00$1.00$390.00$1.00$390.00$2.00$780.00
2452.510STEEL H-PILING DRIVEN 12"LIN FT900$1.00$900.00$1.00$900.00$1.00$900.00$1.00$900.00$2.00$1,800.00
2452.511STEEL H-PILING DELIVERED 12"LIN FT900$28.00$25,200.00$3.00$2,700.00$34.00$30,600.00$28.28$25,452.00$38.00$34,200.00
2452.511STEEL H-PILING DELIVERED 10"LIN FT390$22.00$8,580.00$2.00$780.00$26.00$10,140.00$22.40$8,736.00$32.00$12,480.00
2452.520STEEL H-TEST PILE 100 FT LONG 12"EACH2$10,000.00$20,000.00$16,000.00$32,000.00$5,000.00$10,000.00$10,979.30$21,958.60$12,000.00$24,000.00
2452.520STEEL H-TEST PILE 70 FT LONG 10"EACH1$7,000.00$7,000.00$8,000.00$8,000.00$4,500.00$4,500.00$9,022.72$9,022.72$7,000.00$7,000.00
2452.520STEEL H-TEST PILE 80 FT LONG 10"EACH1$8,000.00$8,000.00$10,000.00$10,000.00$4,750.00$4,750.00$9,022.72$9,022.72$8,000.00$8,000.00
2452.602PILE TIP PROTECTION 12"EACH12$150.00$1,800.00$100.00$1,200.00$150.00$1,800.00$116.31$1,395.72$120.00$1,440.00
2452.602PILE TIP PROTECTION 10"EACH8$100.00$800.00$90.00$720.00$125.00$1,000.00$98.73$789.84$100.00$800.00
2452.60320" STEEL PILE SHELLSLIN FT240$32.00$7,680.00$50.00$12,000.00$55.00$13,200.00$56.73$13,615.20$85.00$20,400.00
2501.51118" CS PIPE CULVERTLIN FT36$28.00$1,008.00$20.00$720.00$28.00$1,008.00$28.00$1,008.00$28.00$1,008.00
2501.51518" GS PIPE APRONEACH2$160.00$320.00$205.00$410.00$160.00$320.00$160.00$320.00$160.00$320.00
2511.501RANDOM RIPRAP CLASS IIICU YD375$48.00$18,000.00$48.00$18,000.00$61.25$22,968.75$63.62$23,857.50$55.00$20,625.00
2545.509CONDUIT SYSTEM (TELEPHONE)LUMP SUM1$4,670.43$4,670.43$4,675.00$4,675.00$7,000.00$7,000.00$5,797.01$5,797.01$4,000.00$4,000.00
2563.601TRAFFIC CONTROLLUMP SUM0.09$2,940.00$264.60$2,940.00$264.60$2,940.00$264.60$11,200.00$1,008.00$3,000.00$270.00
2563.601TRAFFIC CONTROLLUMP SUM0.91$2,940.00$2,675.40$2,940.00$2,675.40$2,940.00$2,675.40$2,800.00$2,548.00$3,000.00$2,730.00
2573.502SILT FENCE, TYPE MACHINE SLICEDLIN FT1,056$1.55$1,636.80$1.55$1,636.80$1.55$1,636.80$1.50$1,584.00$1.55$1,636.80
2575.555TURF ESTABLISHMENTLUMP SUM1$1,200.00$1,200.00$1,200.00$1,200.00$1,200.00$1,200.00$1,500.00$1,500.00$1,200.00$1,200.00
 Totals for project SP 07-599-51 $466,833.00 $503,002.23 $545,253.05 $566,375.26 $624,780.55
 
Contract Total:$466,833.00$503,002.23$545,253.05$566,375.26$624,780.55