Blue Earth County

Welcome, Guest!
Log in | Employee Login | License
 

Bid Abstract

SP 007-612-011 - CSAH 12 (Stage 4)Mathiowetz Construction Co. OMG Midwest Inc. dba Minnesota Paving & Materials LUNDA CONSTRUCTION CO. MINNOWA CONSTRUCTION CO. Central Specialties, Inc. 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLUMP SUM1$299,217.00$299,217.00$270,000.00$270,000.00$570,450.00$570,450.00$523,000.00$523,000.00$570,000.00$570,000.00
2102.502PAVEMENT MARKING REMOVALLIN FT300$1.00$300.00$0.85$255.00$1.00$300.00$1.00$300.00$1.00$300.00
2104.501REMOVE PIPE CULVERTSLIN FT166$6.00$996.00$4.20$697.20$6.00$996.00$10.00$1,660.00$10.00$1,660.00
2104.505REMOVE CONCRETE PAVEMENTSQ YD1,384$6.00$8,304.00$5.50$7,612.00$6.00$8,304.00$6.00$8,304.00$10.00$13,840.00
2104.505REMOVE BITUMINOUS PAVEMENTSQ YD4,579$2.50$11,447.50$2.90$13,279.10$2.50$11,447.50$2.00$9,158.00$7.00$32,053.00
2104.509REMOVE METAL APRONEACH2$75.00$150.00$104.00$208.00$75.00$150.00$100.00$200.00$200.00$400.00
2104.509REMOVE CONCRETE APRONEACH1$125.00$125.00$500.00$500.00$125.00$125.00$300.00$300.00$250.00$250.00
2104.509REMOVE SIGN TYPE AEACH4$550.00$2,200.00$570.00$2,280.00$550.00$2,200.00$550.00$2,200.00$550.00$2,200.00
2104.509REMOVE SIGN TYPE CEACH5$55.00$275.00$57.00$285.00$55.00$275.00$55.00$275.00$55.00$275.00
2104.509REMOVE SIGN TYPE DEACH1$90.00$90.00$92.00$92.00$90.00$90.00$90.00$90.00$90.00$90.00
2104.511SAWING CONCRETE PAVEMENT (FULL DEPTH)LIN FT4,312$4.00$17,248.00$4.15$17,894.80$6.00$25,872.00$4.00$17,248.00$5.13$22,120.56
2104.513SAWING BITUMINOUS PAVEMENT (FULL DEPTH)LIN FT1,311$1.55$2,032.05$1.40$1,835.40$5.13$6,725.43$1.55$2,032.05$1.00$1,311.00
2104.523SALVAGE CONCRETE APRONEACH1$250.00$250.00$155.00$155.00$250.00$250.00$300.00$300.00$200.00$200.00
2104.523SALVAGE SIGN PANEL TYPE AEACH1$350.00$350.00$360.00$360.00$350.00$350.00$350.00$350.00$350.00$350.00
2105.501COMMON EXCAVATION (P)CU YD129,789$3.25$421,814.25$4.40$571,071.60$3.25$421,814.25$3.25$421,814.25$2.85$369,898.65
2105.507SUBGRADE EXCAVATION (P)CU YD587$4.25$2,494.75$3.90$2,289.30$4.25$2,494.75$4.00$2,348.00$2.85$1,672.95
2105.522SELECT GRANULAR BORROW (CV)CU YD9,974$14.85$148,113.90$13.85$138,139.90$16.25$162,077.50$16.45$164,072.30$21.00$209,454.00
2105.522SELECT GRANULAR BORROW MOD 10% (CV)CU YD1,112$18.00$20,016.00$13.85$15,401.20$18.40$20,460.80$20.20$22,462.40$24.50$27,244.00
2105.523COMMON BORROW (CV) (P)CU YD845$0.01$8.45$3.90$3,295.50$0.01$8.45$0.01$8.45$3.50$2,957.50
2112.619AGGREGATE BASE PREPARATION (STRINGLINE)ROAD STA112.39$0.01$1.12$140.00$15,734.60$0.01$1.12$135.00$15,172.65$250.00$28,097.50
2123.610DOZER (D6 OR APPROVED EQUIPMENT)HOUR8$165.00$1,320.00$182.00$1,456.00$165.00$1,320.00$175.00$1,400.00$150.00$1,200.00
2123.610TRACTOR MOUNTED BACKHOEHOUR6$140.00$840.00$152.00$912.00$140.00$840.00$200.00$1,200.00$150.00$900.00
2211.501AGGREGATE BASE CLASS 3TON42,238$9.75$411,820.50$10.00$422,380.00$10.65$449,834.70$10.00$422,380.00$13.00$549,094.00
2211.501AGGREGATE BASE CLASS 5TON45,765$12.28$561,994.20$13.00$594,945.00$12.50$572,062.50$13.00$594,945.00$14.50$663,592.50
2221.501AGGREGATE SHOULDERING CLASS 2TON730$19.50$14,235.00$20.00$14,600.00$19.50$14,235.00$20.75$15,147.50$25.00$18,250.00
2301.511STRUCTURAL CONCRETECU YD3,283$104.00$341,432.00$114.00$374,262.00$112.03$367,794.49$112.03$367,794.49$112.03$367,794.49
2301.531EXPANSION JOINTS DESIGN E8H (P)LIN FT158$40.00$6,320.00$41.00$6,478.00$40.00$6,320.00$65.00$10,270.00$40.00$6,320.00
2301.538DOWEL BAREACH7,118$8.50$60,503.00$8.90$63,350.20$8.68$61,784.24$8.68$61,784.24$8.68$61,784.24
2301.553BRIDGE APPROACH PANELS (P)SQ YD351$65.00$22,815.00$66.00$23,166.00$65.00$22,815.00$230.00$80,730.00$65.00$22,815.00
2301.602DRILL & GROUT DOWEL BAR (EPOXY COATED)EACH1,560$11.00$17,160.00$9.00$14,040.00$8.68$13,540.80$8.68$13,540.80$8.68$13,540.80
2301.604CONCRETE PAVEMENT 9.0"SQ YD13,124$16.00$209,984.00$13.00$170,612.00$12.44$163,262.56$12.44$163,262.56$12.44$163,262.56
2301.608REINFORCEMENT BARS (EPOXY COATED)POUND11,788$1.00$11,788.00$2.40$28,291.20$2.32$27,348.16$2.32$27,348.16$2.32$27,348.16
2357.502BITUMINOUS MATERIAL FOR TACK COATGALLON4,339$2.25$9,762.75$2.20$9,545.80$2.25$9,762.75$2.25$9,762.75$1.00$4,339.00
2360.501TYPE SP 12.5 WEARING COURSE MIXTURE (4,C)TON10,145$79.95$811,092.75$79.00$801,455.00$79.95$811,092.75$81.00$821,745.00$82.56$837,571.20
2360.501TYPE SP 12.5 WEARING COURSE MIXTURE (2,B)TON1,284$76.00$97,584.00$76.00$97,584.00$76.00$97,584.00$76.50$98,226.00$90.59$116,317.56
2360.502TYPE SP 12.5 NON WEARING COURSE MIXTURE (4,C)TON6,310$75.95$479,244.50$77.00$485,870.00$75.95$479,244.50$76.70$483,977.00$76.48$482,588.80
2401.501STRUCTURAL CONCRETE (1A43) (P)CU YD305$450.00$137,250.00$455.00$138,775.00$450.00$137,250.00$400.00$122,000.00$450.00$137,250.00
2401.501STRUCTURAL CONCRETE (3Y43) (P)CU YD365$450.00$164,250.00$455.00$166,075.00$450.00$164,250.00$500.00$182,500.00$450.00$164,250.00
2401.512BRIDGE SLAB CONCRETE (3Y36A) (P)SQ FT18,578$12.00$222,936.00$12.25$227,580.50$12.00$222,936.00$15.00$278,670.00$12.00$222,936.00
2401.513TYPE F (TL-4) RAILING CONCRETE (3Y46A) (P)LIN FT276$63.00$17,388.00$64.00$17,664.00$63.00$17,388.00$70.00$19,320.00$63.00$17,388.00
2401.513TYPE MOD P-1 (TL-2) RAILING CONCRETE (3Y46A) (P)LIN FT276$65.00$17,940.00$66.00$18,216.00$65.00$17,940.00$70.00$19,320.00$65.00$17,940.00
2401.515SIDEWALK CONCRETE (3Y46A) (P)SQ FT3,308$5.00$16,540.00$5.10$16,870.80$5.00$16,540.00$12.00$39,696.00$5.00$16,540.00
2401.516RAISED MEDIAN CONCRETE (3Y46A) (P)SQ FT1,103$5.00$5,515.00$5.10$5,625.30$5.00$5,515.00$11.00$12,133.00$5.00$5,515.00
2401.541REINFORCEMENT BARS (P)POUND24,230$1.00$24,230.00$1.05$25,441.50$1.00$24,230.00$1.00$24,230.00$1.00$24,230.00
2401.541REINFORCEMENT BARS (EPOXY COATED) (P)POUND191,220$1.10$210,342.00$1.10$210,342.00$1.10$210,342.00$1.10$210,342.00$1.10$210,342.00
2401.601STRUCTURE EXCAVATIONLUMP SUM1$13,000.00$13,000.00$15,000.00$15,000.00$13,000.00$13,000.00$15,000.00$15,000.00$13,000.00$13,000.00
2402.583ORNAMENTAL METAL RAILING TYPE SPECIAL (P)LIN FT270$125.00$33,750.00$128.00$34,560.00$125.00$33,750.00$130.00$35,100.00$125.00$33,750.00
2402.595BEARING ASSEMBLYEACH36$1,000.00$36,000.00$1,010.00$36,360.00$1,000.00$36,000.00$750.00$27,000.00$1,000.00$36,000.00
2404.501CONCRETE WEARING COURSE (3U17A) (P)SQ FT16,540$2.00$33,080.00$2.10$34,734.00$2.00$33,080.00$4.60$76,084.00$2.00$33,080.00
2404.618BLASTING (SPECIAL)SQ FT16,540$0.30$4,962.00$0.31$5,127.40$0.30$4,962.00$0.50$8,270.00$0.30$4,962.00
2405.502PRESTRESSED CONCRETE BEAMS MN54 (P)LIN FT2,098$180.00$377,640.00$182.00$381,836.00$180.00$377,640.00$190.00$398,620.00$180.00$377,640.00
2405.511DIAPHRAGMS FOR TYPE MN54 PREST BEAMS (P)LIN FT448$75.00$33,600.00$76.00$34,048.00$75.00$33,600.00$60.00$26,880.00$75.00$33,600.00
2411.618ARCHITECTURAL CONCRETE TEXTURE (FRACTURED FIN) (P)SQ FT1,157$50.00$57,850.00$51.00$59,007.00$50.00$57,850.00$15.00$17,355.00$50.00$57,850.00
2411.618ARCHITECTURAL SURFACE FINISH (SINGLE COLOR) (P)SQ FT1,157$1.25$1,446.25$1.30$1,504.10$1.25$1,446.25$3.00$3,471.00$1.25$1,446.25
2452.507C-I-P CONCRETE PILING DELIVERED 12"LIN FT15,140$32.00$484,480.00$32.50$492,050.00$32.00$484,480.00$29.00$439,060.00$32.00$484,480.00
2452.508C-I-P CONCRETE PILING DRIVEN 12"LIN FT15,140$1.00$15,140.00$1.05$15,897.00$1.00$15,140.00$1.00$15,140.00$1.00$15,140.00
2452.519C-I-P CONCRETE TEST PILE 135 FT LONG 12"EACH4$6,000.00$24,000.00$6,100.00$24,400.00$6,000.00$24,000.00$18,000.00$72,000.00$6,000.00$24,000.00
2452.519C-I-P CONCRETE TEST PILE 125 FT LONG 12"EACH2$5,000.00$10,000.00$5,200.00$10,400.00$5,000.00$10,000.00$15,000.00$30,000.00$5,000.00$10,000.00
2452.527PILE REDRIVINGEACH34$100.00$3,400.00$102.00$3,468.00$100.00$3,400.00$100.00$3,400.00$100.00$3,400.00
2452.602PILE ANALYSISEACH6$1,500.00$9,000.00$1,525.00$9,150.00$1,500.00$9,000.00$2,500.00$15,000.00$1,500.00$9,000.00
2452.603BITUMEN PILE COATINGLIN FT6,160$10.00$61,600.00$10.20$62,832.00$10.00$61,600.00$6.00$36,960.00$10.00$61,600.00
2501.51118" RC PIPE CULVERT CLASS IVLIN FT312$32.00$9,984.00$40.00$12,480.00$32.00$9,984.00$33.00$10,296.00$50.00$15,600.00
2501.51124" RC PIPE CULVERT CLASS IVLIN FT282$40.25$11,350.50$52.00$14,664.00$40.25$11,350.50$41.00$11,562.00$65.00$18,330.00
2501.51142" RC PIPE CULVERT CLASS IVLIN FT12$100.00$1,200.00$142.00$1,704.00$100.00$1,200.00$105.00$1,260.00$120.00$1,440.00
2501.51512" RC PIPE APRONEACH15$309.00$4,635.00$279.00$4,185.00$309.00$4,635.00$370.00$5,550.00$475.00$7,125.00
2501.51515" RC PIPE APRONEACH1$337.00$337.00$325.00$325.00$337.00$337.00$390.00$390.00$550.00$550.00
2501.51518" RC PIPE APRONEACH10$325.00$3,250.00$345.00$3,450.00$325.00$3,250.00$450.00$4,500.00$525.00$5,250.00
2501.51524" RC PIPE APRONEACH3$392.00$1,176.00$425.00$1,275.00$392.00$1,176.00$520.00$1,560.00$570.00$1,710.00
2501.52128" SPAN RC PIPE-ARCH CULVERT CLASS IIALIN FT168$61.00$10,248.00$75.00$12,600.00$61.00$10,248.00$56.00$9,408.00$80.00$13,440.00
2501.52528" SPAN RC PIPE-ARCH APRONEACH2$382.00$764.00$415.00$830.00$382.00$764.00$670.00$1,340.00$510.00$1,020.00
2501.573INSTALL CONCRETE APRONEACH1$250.00$250.00$204.00$204.00$250.00$250.00$300.00$300.00$250.00$250.00
2502.5014" PRECAST CONCRETE HEADWALLEACH33$120.00$3,960.00$122.00$4,026.00$120.00$3,960.00$120.00$3,960.00$120.00$3,960.00
2502.502DRAINAGE SYSTEM TYPE (B910)LUMP SUM1$1,500.00$1,500.00$1,525.00$1,525.00$1,500.00$1,500.00$3,000.00$3,000.00$1,500.00$1,500.00
2502.5214" TP PIPE DRAINLIN FT1,416$6.75$9,558.00$7.00$9,912.00$6.75$9,558.00$6.75$9,558.00$6.75$9,558.00
2502.5416" PERF PVC PIPE DRAIN (SDR35)LIN FT2,289$14.50$33,190.50$7.60$17,396.40$8.00$18,312.00$15.00$34,335.00$10.00$22,890.00
2502.5414" PERF PE PIPE DRAINLIN FT32,145$6.12$196,727.40$6.25$200,906.25$6.12$196,727.40$6.12$196,727.40$6.12$196,727.40
2503.54112" RC PIPE SEWER DESIGN 3006 CLASS VLIN FT2,254$26.00$58,604.00$22.00$49,588.00$26.00$58,604.00$25.00$56,350.00$45.00$101,430.00
2503.54115" RC PIPE SEWER DESIGN 3006 CLASS VLIN FT50$30.00$1,500.00$27.00$1,350.00$30.00$1,500.00$29.00$1,450.00$46.00$2,300.00
2503.54118" RC PIPE SEWER DESIGN 3006 CLASS IVLIN FT571$32.00$18,272.00$32.00$18,272.00$32.00$18,272.00$30.00$17,130.00$48.00$27,408.00
2503.54130" RC PIPE SEWER DESIGN 3006 CLASS IVLIN FT57$59.00$3,363.00$60.00$3,420.00$59.00$3,363.00$55.00$3,135.00$73.00$4,161.00
2503.602CONNECT TO EXISTING STORM SEWEREACH1$500.00$500.00$520.00$520.00$500.00$500.00$400.00$400.00$250.00$250.00
2506.501CONSTRUCT DRAINAGE STRUCTURE DESIGN 48-4020LIN FT34.26$210.00$7,194.60$270.00$9,250.20$210.00$7,194.60$210.00$7,194.60$230.00$7,879.80
2506.501CONSTRUCT DRAINAGE STRUCTURE DESIGN 48-4022LIN FT91.04$225.00$20,484.00$248.00$22,577.92$225.00$20,484.00$225.00$20,484.00$250.00$22,760.00
2506.501CONSTRUCT DRAINAGE STRUCTURE DESIGN 60-4020LIN FT7.28$494.00$3,596.32$460.00$3,348.80$494.00$3,596.32$410.00$2,984.80$720.00$5,241.60
2506.501CONSTRUCT DRAINAGE STRUCTURE DESIGN 60-4022LIN FT8.38$350.00$2,933.00$400.00$3,352.00$350.00$2,933.00$315.00$2,639.70$550.00$4,609.00
2506.501CONSTRUCT DRAINAGE STRUCTURE DESIGN HLIN FT21$174.00$3,654.00$260.00$5,460.00$174.00$3,654.00$170.00$3,570.00$350.00$7,350.00
2506.501CONSTRUCT DRAINAGE STRUCTURE DESIGN NLIN FT2.54$198.00$502.92$255.00$647.70$198.00$502.92$170.00$431.80$420.00$1,066.80
2506.501CONSTRUCT DRAINAGE STRUCTURE DESIGN SPECIAL R-1LIN FT99.45$210.00$20,884.50$295.00$29,337.75$210.00$20,884.50$201.00$19,989.45$260.00$25,857.00
2506.516CASTING ASSEMBLYEACH49$603.00$29,547.00$475.00$23,275.00$603.00$29,547.00$550.00$26,950.00$620.00$30,380.00
2511.501RANDOM RIPRAP CLASS IIICU YD40$56.00$2,240.00$51.00$2,040.00$56.00$2,240.00$55.00$2,200.00$60.00$2,400.00
2511.511GRANULAR FILTERCU YD12$50.00$600.00$15.20$182.40$50.00$600.00$25.00$300.00$50.00$600.00
2514.501CONCRETE SLOPE PAVING (P)SQ YD422$65.00$27,430.00$66.00$27,852.00$65.00$27,430.00$100.00$42,200.00$65.00$27,430.00
2521.5014" CONCRETE WALKSQ FT5,237$2.81$14,715.97$2.90$15,187.30$2.81$14,715.97$2.81$14,715.97$3.40$17,805.80
2521.5016" CONCRETE WALKSQ FT997$8.15$8,125.55$8.45$8,424.65$8.15$8,125.55$8.15$8,125.55$5.05$5,034.85
2531.501CONCRETE CURB & GUTTER DESIGN B424LIN FT7,972$10.48$83,546.56$10.70$85,300.40$10.48$83,546.56$10.48$83,546.56$12.54$99,968.88
2531.501CONCRETE CURB & GUTTER DESIGN D424LIN FT989$11.92$11,788.88$12.15$12,016.35$11.92$11,788.88$11.92$11,788.88$13.30$13,153.70
2531.501CONCRETE CURB & GUTTER DESIGN B624LIN FT6,880$12.03$82,766.40$12.25$84,280.00$12.03$82,766.40$12.03$82,766.40$12.80$88,064.00
2531.501CONCRETE CURB & GUTTER DESIGN S524LIN FT854$15.66$13,373.64$16.25$13,877.50$15.66$13,373.64$15.66$13,373.64$14.04$11,990.16
2531.502CONCRETE CURB DESIGN B6LIN FT694$13.00$9,022.00$13.50$9,369.00$13.00$9,022.00$13.00$9,022.00$10.13$7,030.22
2531.502CONCRETE CURB DESIGN B8LIN FT634$14.27$9,047.18$14.95$9,478.30$14.27$9,047.18$14.27$9,047.18$7.12$4,514.08
2531.5034" CONCRETE MEDIANSQ YD3,293$21.46$70,667.78$22.00$72,446.00$21.46$70,667.78$21.46$70,667.78$29.71$97,835.03
2531.5078" CONCRETE DRIVEWAY PAVEMENTSQ YD1,038$45.54$47,270.52$46.00$47,748.00$45.54$47,270.52$45.54$47,270.52$45.24$46,959.12
2531.618TRUNCATED DOMESSQ FT256$32.50$8,320.00$33.00$8,448.00$32.50$8,320.00$32.50$8,320.00$35.96$9,205.76
2533.507PORTABLE PRECAST CONCRETE BARRIER DESIGN 8337LIN FT5,297$15.50$82,103.50$15.85$83,957.45$15.00$79,455.00$15.00$79,455.00$15.50$82,103.50
2533.507RELOCATE PORTABLE PRECAST CONCRETE BARRIER DESIGN 8337LIN FT2,246$3.25$7,299.50$3.40$7,636.40$2.75$6,176.50$4.00$8,984.00$3.25$7,299.50
2545.501ELECTRIC LIGHT SYSTEMLUMP SUM1$182,514.00$182,514.00$188,000.00$188,000.00$182,514.00$182,514.00$190,000.00$190,000.00$182,514.00$182,514.00
2545.509CONDUIT SYSTEM, BRIDGE (FUTURE)LUMP SUM1$4,305.00$4,305.00$4,400.00$4,400.00$2,750.00$2,750.00$4,500.00$4,500.00$4,305.00$4,305.00
2545.509CONDUIT SYSTEM, BRIDGE (LIGHTING)LUMP SUM1$4,305.00$4,305.00$4,400.00$4,400.00$4,305.00$4,305.00$4,500.00$4,500.00$4,305.00$4,305.00
2554.501TRAFFIC BARRIER DESIGN SPECIALLIN FT50$64.75$3,237.50$66.00$3,300.00$64.75$3,237.50$64.75$3,237.50$64.75$3,237.50
2554.501TRAFFIC BARRIER DESIGN B8338LIN FT850$17.00$14,450.00$17.50$14,875.00$17.00$14,450.00$17.00$14,450.00$17.00$14,450.00
2554.521ANCHORAGE ASSEMBLY-PLATE BEAMEACH2$395.00$790.00$410.00$820.00$395.00$790.00$395.00$790.00$395.00$790.00
2554.523END TREATMENT-TANGENT TERMINALEACH4$2,075.00$8,300.00$2,100.00$8,400.00$2,075.00$8,300.00$2,075.00$8,300.00$2,075.00$8,300.00
2554.602IMPACT ATTENUATOR BARRELSEACH76$150.00$11,400.00$155.00$11,780.00$150.00$11,400.00$150.00$11,400.00$150.00$11,400.00
2554.602RELOCATE IMPACT ATTENUATOR BARRELSEACH94$25.00$2,350.00$26.00$2,444.00$25.00$2,350.00$45.00$4,230.00$25.00$2,350.00
2557.501WIRE FENCE DESIGN 60-9322LIN FT5,097$4.95$25,230.15$5.10$25,994.70$4.95$25,230.15$5.00$25,485.00$4.95$25,230.15
2557.521WOOD BRACE ASSEMBLYEACH48$225.00$10,800.00$230.00$11,040.00$225.00$10,800.00$225.00$10,800.00$225.00$10,800.00
2563.601TRAFFIC CONTROLLUMP SUM1$24,000.00$24,000.00$45,000.00$45,000.00$24,000.00$24,000.00$19,000.00$19,000.00$24,000.00$24,000.00
2563.602RAISED PAVEMENT MARKER TEMPORARYEACH368$1.40$515.20$1.45$533.60$1.40$515.20$1.45$533.60$1.40$515.20
2563.602PORTABLE CONCRETE BARRIER DELINEATOREACH229$4.00$916.00$4.15$950.35$4.00$916.00$4.25$973.25$4.00$916.00
2564.522STRUCTURAL STEEL-POSTS FOR TYPE A SIGNSPOUND6,433.5$3.05$19,622.18$3.20$20,587.20$3.05$19,622.18$3.05$19,622.18$3.05$19,622.18
2564.522STRUCTURAL STEEL-TRUSSES FOR OH SIGNS BRIDGE MOUNTED (P)POUND1,060$4.65$4,929.00$4.70$4,982.00$4.65$4,929.00$5.00$5,300.00$4.65$4,929.00
2564.531SIGN PANELS TYPE ASQ FT747.5$23.35$17,454.13$24.00$17,940.00$23.35$17,454.13$23.35$17,454.13$23.35$17,454.13
2564.531SIGN PANELS TYPE CSQ FT955.675$28.05$26,806.68$28.50$27,236.74$28.05$26,806.68$28.05$26,806.68$28.05$26,806.68
2564.531SIGN PANELS TYPE DSQ FT101.5$25.45$2,583.18$26.00$2,639.00$25.45$2,583.18$25.45$2,583.18$25.45$2,583.18
2564.531SIGN PANELS TYPE OVERLAYSQ FT36$11.95$430.20$12.25$441.00$11.95$430.20$11.95$430.20$11.95$430.20
2564.531SIGN PANELS OVERLAY TYPE ASQ FT44$17.35$763.40$18.00$792.00$17.35$763.40$17.35$763.40$17.35$763.40
2564.537INSTALL SIGN TYPE OH (BR MOUNT)EACH1$390.65$390.65$400.00$400.00$390.65$390.65$390.65$390.65$390.65$390.65
2564.550DELINEATOR TYPE X4-6EACH16$81.45$1,303.20$82.00$1,312.00$81.45$1,303.20$81.45$1,303.20$81.45$1,303.20
2564.551REFERENCE POST MARKEREACH1$155.00$155.00$160.00$160.00$155.00$155.00$155.00$155.00$155.00$155.00
2564.552HAZARD MARKER X4-2EACH4$91.75$367.00$93.00$372.00$91.75$367.00$91.75$367.00$91.75$367.00
2571.505DECIDUOUS SHRUB NO 2 CONTSHRUB486$15.02$7,299.72$15.20$7,387.20$15.02$7,299.72$15.02$7,299.72$15.02$7,299.72
2571.505DECIDUOUS SHRUB NO 10 CONTSHRUB14$24.04$336.56$25.00$350.00$24.04$336.56$24.04$336.56$24.04$336.56
2571.507PERENNIAL NO 1 CONTPLANT1,292$6.68$8,630.56$7.00$9,044.00$6.68$8,630.56$6.68$8,630.56$6.68$8,630.56
2573.502SILT FENCE, TYPE MACHINE SLICEDLIN FT19,291$1.40$27,007.40$1.45$27,971.95$1.40$27,007.40$1.40$27,007.40$1.40$27,007.40
2573.512TEMPORARY DITCH CHECK TYPE 2LIN FT2,370$2.00$4,740.00$2.10$4,977.00$2.00$4,740.00$2.00$4,740.00$2.00$4,740.00
2573.513TEMPORARY DITCH CHECK TYPE 7CU YD375$25.00$9,375.00$41.00$15,375.00$25.00$9,375.00$35.00$13,125.00$60.00$22,500.00
2573.520SEDIMENT REMOVAL BACKHOEHOUR12$150.00$1,800.00$135.00$1,620.00$150.00$1,800.00$200.00$2,400.00$160.00$1,920.00
2573.530STORM DRAIN INLET PROTECTIONEACH52$200.00$10,400.00$105.00$5,460.00$200.00$10,400.00$100.00$5,200.00$100.00$5,200.00
2573.540FILTER LOG TYPE WOOD FIBER BIOROLLLIN FT2,420$1.90$4,598.00$2.00$4,840.00$1.90$4,598.00$1.90$4,598.00$1.90$4,598.00
2573.550EROSION CONTROL SUPERVISORLUMP SUM1$5,000.00$5,000.00$8,500.00$8,500.00$25,000.00$25,000.00$5,000.00$5,000.00$10,000.00$10,000.00
2575.501SEEDINGACRE50.7941$120.00$6,095.29$122.00$6,196.88$120.00$6,095.29$120.00$6,095.29$120.00$6,095.29
2575.502SEED MIXTURE 150POUND1,008$2.05$2,066.40$2.15$2,167.20$2.05$2,066.40$2.05$2,066.40$2.05$2,066.40
2575.502SEED MIXTURE 270POUND265$1.65$437.25$1.75$463.75$1.65$437.25$1.65$437.25$1.65$437.25
2575.502SEED MIXTURE 280POUND1,170$2.45$2,866.50$2.60$3,042.00$2.45$2,866.50$2.45$2,866.50$2.45$2,866.50
2575.511MULCH MATERIAL TYPE 1TON91.46$150.00$13,719.00$155.00$14,176.30$150.00$13,719.00$150.00$13,719.00$150.00$13,719.00
2575.519DISK ANCHORINGACRE45.743$60.00$2,744.58$62.00$2,836.07$60.00$2,744.58$60.00$2,744.58$60.00$2,744.58
2575.523EROSION CONTROL BLANKETS CATEGORY 4SQ YD19,030$1.00$19,030.00$1.05$19,981.50$1.00$19,030.00$1.00$19,030.00$1.00$19,030.00
2575.525EROSION STABILIZATION MAT CLASS 4SQ YD700$11.00$7,700.00$11.50$8,050.00$11.00$7,700.00$11.00$7,700.00$11.00$7,700.00
2575.532COMMERCIAL FERTILIZER ANALYSIS 20-10-20POUND8,956$0.55$4,925.80$0.60$5,373.60$0.55$4,925.80$0.55$4,925.80$0.55$4,925.80
2575.560HYDRAULIC SOIL STABILIZER TYPE 5POUND52,923$0.65$34,399.95$0.70$37,046.10$0.65$34,399.95$0.65$34,399.95$0.65$34,399.95
2575.607MULCH MATERIAL TYPE SPECIALCU YD146$31.50$4,599.00$33.00$4,818.00$31.50$4,599.00$31.50$4,599.00$31.50$4,599.00
2581.501REMOVABLE PREFORMED PLASTIC MARKINGLIN FT12,322$1.25$15,402.50$1.30$16,018.60$1.30$16,018.60$1.30$16,018.60$1.25$15,402.50
2581.603REMOVABLE PREFORMED PLASTIC MASK (BLACK)LIN FT3,426$2.25$7,708.50$2.35$8,051.10$2.30$7,879.80$2.30$7,879.80$2.25$7,708.50
2582.501PAVEMENT MESSAGE (LEFT ARROW) POLY PREFORMEACH6$290.00$1,740.00$300.00$1,800.00$290.00$1,740.00$290.00$1,740.00$290.00$1,740.00
2582.501PAVEMENT MESSAGE (RIGHT ARROW) POLY PREFORMEACH11$290.00$3,190.00$305.00$3,355.00$290.00$3,190.00$290.00$3,190.00$290.00$3,190.00
2582.501PAVEMENT MESSAGE (THRU ARROW) POLY PREFORMEACH2$290.00$580.00$305.00$610.00$290.00$580.00$290.00$580.00$290.00$580.00
2582.501PAVEMENT MESSAGE (LEFT-THRU ARROW) POLY PREFORMEACH2$580.00$1,160.00$600.00$1,200.00$580.00$1,160.00$580.00$1,160.00$580.00$1,160.00
2582.501PAVEMENT MESSAGE (THRU FISH-HOOK ARROW) POLY PREFORMEACH5$450.00$2,250.00$470.00$2,350.00$450.00$2,250.00$450.00$2,250.00$450.00$2,250.00
2582.501PAVEMENT MESSAGE (LEFT FISH HOOK ARROW WITH DOT) POLY PREFORMEACH2$450.00$900.00$470.00$940.00$450.00$900.00$450.00$900.00$450.00$900.00
2582.501PAVEMENT MESSAGE (THRU FISH-HOOK ARROW WITH DOT) POLY PREFORMEACH2$550.00$1,100.00$570.00$1,140.00$550.00$1,100.00$550.00$1,100.00$550.00$1,100.00
2582.501PAVEMENT MESSAGE (LT-THRU FISH-HOOK ARROW WITH DOT) POLY PREFORMEACH4$900.00$3,600.00$940.00$3,760.00$900.00$3,600.00$900.00$3,600.00$900.00$3,600.00
2582.5024" SOLID LINE WHITE-EPOXYLIN FT29,600$0.40$11,840.00$0.45$13,320.00$0.40$11,840.00$0.40$11,840.00$0.40$11,840.00
2582.50224" SOLID LINE WHITE-EPOXYLIN FT295$14.00$4,130.00$14.50$4,277.50$14.00$4,130.00$14.00$4,130.00$14.00$4,130.00
2582.5024" BROKEN LINE WHITE-EPOXYLIN FT2,020$0.40$808.00$0.45$909.00$0.40$808.00$0.40$808.00$0.40$808.00
2582.5024" DOTTED LINE WHITE-EPOXYLIN FT45$2.80$126.00$2.90$130.50$2.80$126.00$2.80$126.00$2.80$126.00
2582.50218" DOTTED LINE WHITE-EPOXYLIN FT120$7.85$942.00$8.20$984.00$7.85$942.00$7.85$942.00$7.85$942.00
2582.5024" SOLID LINE YELLOW-EPOXYLIN FT6,300$0.46$2,898.00$0.50$3,150.00$0.46$2,898.00$0.46$2,898.00$0.46$2,898.00
2582.5024" BROKEN LINE YELLOW-EPOXYLIN FT260$0.46$119.60$0.50$130.00$0.46$119.60$0.46$119.60$0.46$119.60
2582.5028" SOLID LINE WHITE-POLY PREFORM (GROUND IN)LIN FT800$6.00$4,800.00$6.30$5,040.00$6.00$4,800.00$6.00$4,800.00$6.00$4,800.00
2582.5028" DOTTED LINE WHITE-POLY PREFORM (GROUND IN)LIN FT200$6.00$1,200.00$6.30$1,260.00$6.00$1,200.00$6.00$1,200.00$6.00$1,200.00
2582.5028" DOTTED LINE WHITE-PAINTLIN FT30$2.80$84.00$2.90$87.00$2.80$84.00$2.80$84.00$2.80$84.00
2582.50224" SOLID LINE YELLOW-EPOXYLIN FT35$14.00$490.00$14.65$512.75$14.00$490.00$14.00$490.00$14.00$490.00
 Totals for project SP 007-612-011 $7,556,908.27 $7,818,923.76 $7,897,395.20 $8,056,750.81 $8,321,672.00
 
Contract Total:$7,556,908.27$7,818,923.76$7,897,395.20$8,056,750.81$8,321,672.00