The following information is intended to provide guidance to bidders by providing the answers given to questions asked by other bidders.

Q: Can Construction Begin earlier than the specified April 15, 2013 date?
A: The intent of the Contract Start Date is to allow time for the Contractor to order all required materials for the project. Typically there is a period of time required for approval, construction, and delivery of the precast concrete box beams. The Contractor may be allowed to begin construction prior to the specified contract start date if the Contractor can prove to the Engineer that all necessary materials will be delivered and constructed in a reasonable timeline as approved by the Engineer. The Contractor is to continuously persue construction after road closure without periods of inactivity.

Q: What is the Spring Load Restriction for CSAH 46?
A: 10 TONS